Multiple Choice
Answer the following questions using the information below:
The tool crib at a large manufacturing company is responsible for providing tools to the factory workers on demand. The tool crib has a variable demand. Historically, its demand has ranged from 300 to 500 small tools per day with an average of 400. Diane, the tool crib attendant, works eight hours a day, five days a week. Each order is for one small tool and each small tool takes Diane 1 minute to retrieve from the bins.
-What is the cycle time for an order?
A) 1 minutes per tool
B) 1.5 minutes per tool
C) 2.5 minutes per tool
D) 3.5 minutes per tool
Correct Answer:

Verified
Correct Answer:
Verified
Q44: Brix, Inc., prepares frozen food for fast-food
Q66: Longer manufacturing cycle times increase the inventory
Q112: Manufacturing cycle times affect both revenues and
Q135: Answer the following questions using the information
Q136: Design engineering is an example of _.<br>A)
Q137: Ply Corp manufactures doors.Classify each of the
Q138: Venlaz Corp makes small motorcycles. The monthly
Q141: Answer the following questions using the information
Q143: A tool which indicates how frequently each
Q144: Answer the following questions using the information