To Complete the First Setup on a New Machine Took

Question 154

Multiple Choice

To complete the first setup on a new machine took an employee 300 minutes.Using an 85% cumulative average-time learning curve indicates that the second setup on the new machine is expected to take ________.


A) 127.50 minutes
B) 210 minutes
C) 277.50 minutes
D) 255 minutes

Correct Answer:

verifed

Verified