Multiple Choice
To complete the first setup on a new machine took an employee 100 minutes.Using an 80% incremental unit-time learning model indicates that the second setup on the new machine is expected to take ________.
A) 80 minutes
B) 120 minutes
C) 70 minutes
D) 60 minutes
Correct Answer:

Verified
Correct Answer:
Verified