Accepting a Project with a ________ NPV Makes the Firm

Question 46

Multiple Choice

Accepting a project with a ________ NPV makes the firm worse off financially because the cost of the investment exceeds the ________.


A) positive; present value of future benefits
B) negative; present value of future cash flows
C) negative; present value of present cash flows
D) positive; present value of present cash flows