Multiple Choice
The static budget variance is equal to the sum of ________ and ________.
A) direct materials variance; direct labor variance
B) fixed overhead variance; variable overhead variance
C) flexible budget variance; activity-level variance
D) direct materials price variance; direct materials quantity variance
Correct Answer:

Verified