Multiple Choice
Which of the following is NOT an example of efficient performance?
A) Direct labor hours used per unit were less than expected.
B) Direct material used per unit was less than expected.
C) More outputs were achieved with less inputs than predicted.
D) More outputs were produced than expected.
Correct Answer:

Verified
Correct Answer:
Verified