Multiple Choice
If the direct labor price variance is $800 Favorable and the direct labor usage variance is $700 Unfavorable,then ________.
A) the flexible budget variance for direct labor is $100 Favorable
B) actual total wages paid were $800 more than expected
C) actual labor hours were less than expected
D) actual material prices were less than expected