Multiple Choice
The Cheeseman Company makes tables and the following standards have been developed:
Production of 230 tables was expected in July,but 250 tables were actually completed.Direct materials purchased and used were 2,200 pounds at an actual price of $4.50 per pound.Direct labor cost for the month was $10,620,and the actual pay per hour was $18.00.What is the direct material price variance for July?
A) $800 Favorable
B) $800 Unfavorable
C) $1,100 Favorable
D) $1,100 Unfavorable
Correct Answer:

Verified
Correct Answer:
Verified
Q114: Which of the following statements is FALSE?<br>A)
Q115: Differentiate between a static budget variance and
Q116: If the sales activity variance was $8,000
Q117: The unfavorable variances resulting from ideal standards
Q118: Ideal standards have an adverse effect on
Q120: A static budget is prepared for one
Q121: A flexible budget adjusts for changes in
Q122: Total static budget variances are equal to
Q123: Which statement would NOT be a reason
Q124: The direct materials price variance reflects the