Sandler Company Has Identified the Following Activities Related to Indirect
Question 15
Question 15
Short Answer
Sandler Company has identified the following activities related to indirect production costs: Activity Machine Setup Materials Handling Electric Power Activity Costs $180,000$50,000$20,000 Cost Drivers 1,500 setup hours 12,500 pounds of materials 20,000 kilowatt hours Sandler Company has obtained the following data concerning two products: Number of units produced Direct materials cost Direct labor cost Number of setup hours Pounds of materials used Kilowatt-hours Prodirct A4,000$20,000$12,0001001205001,5001,000 Prodirct B20,000$25,000$20,0002,000 Using activity-based costing,what amount of electric power cost is assigned to Product A and Product B? A)B)C)D) Prodirct A$1,000$3,333$5,000$6,667 Prodirct B$2,000$16,667$15,000$13,333
Correct Answer:
Verified
Unlock this answer now Get Access to more Verified Answers free of charge