LR Kinncaid Company Assembles Steel Components for Trains Calculate the Direct Labour Efficiency Variance
A) £48,000 Favorable
B)
Multiple Choice
LR Kinncaid Company assembles steel components for trains.The standard labour cost per unit is:
3 hours @ £3.20 per hour
The actual results for last period were:
Calculate the direct labour efficiency variance
A) £48,000 favorable
B) £48,000 adverse
C) £1,650 favorable
D) £1,650 adverse
Correct Answer:

Verified
Correct Answer:
Verified
Q13: Which of the following is likely to
Q14: Variable overhead variances are typically in proportion
Q15: Variable overhead price variance can be expressed
Q16: Which of the following statements is INCORRECT?<br>A)
Q17: Fixed overhead expenditure variance can be expressed
Q19: Which of the following would lead to
Q20: LR Kinncaid Company assembles steel components
Q21: Direct labour efficiency variance can be expresses
Q22: Which of the following would be the
Q23: The sales margin volume variance measures the