The LAH company produces product BG,which includes variable overhead standard cost of 5 hours at £15 per hour,based on a budget production of 3,000 units.The actual results for the last period were as follows:
 Production 3,100 Hours incurred 16,000 Variable overhead £235,00\begin{array} { l c } \text { Production } & 3,100 \\\text { Hours incurred } & 16,000 \\\text { Variable overhead } & £ 235,00\end{array}
Calculate the variable overhead efficiency variance.


A) £5,000 favorable
B) £5,000 adverse
C) £7,500 favorable
D) £7,500 adverse