The Following Information Is Provided by Horowitz Systems What Is the Profitability Index for Project C? (Round Your

Question 20

Multiple Choice

The following information is provided by Horowitz Systems:  Project A  Project B  Project C  Project D  Initial investment $426,000$218,000$554,000$502,000 PV of cash inflows $586,000$386,000$820,000$408,000 Payback period (years)  3.63.24.02.0 NPV of project $160,000$168,000$266,000$94,000\begin{array} { | l | r | r | r | r | } \hline & \text { Project A } & \text { Project B } & \text { Project C } & \text { Project D } \\\hline \text { Initial investment } & \$ 426,000 & \$ 218,000 & \$ 554,000 & \$ 502,000 \\\hline \text { PV of cash inflows } & \$ 586,000 & \$ 386,000 & \$ 820,000 & \$ 408,000 \\\hline \text { Payback period (years) } & 3.6 & 3.2 & 4.0 & 2.0 \\\hline \text { NPV of project } & \$ 160,000 & \$ 168,000 & \$ 266,000 & \$ 94,000 \\\hline\end{array} What is the profitability index for Project C? (Round your answer to two decimal places.)


A) 1.48
B) 1.38
C) 1.26
D) 1.22

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions