If the Project Scope Seems Much Greater Than Originally Anticipated

Question 32

Multiple Choice

If the project scope seems much greater than originally anticipated by the customer, it may affect the ____ for performing the work and ____ accomplishing the project objective.


A) resources assigned, help with
B) technical requirements, shorten the time for
C) commitment, accelerate
D) budget and schedule, jeopardize

Correct Answer:

verifed

Verified