Multiple Choice
When several activities need the same limited resource at the same time, the activities with
A) the least slack have first priority.
B) the longest duration have first priority.
C) the near term have first priority.
D) use the most resources have first priority.
Correct Answer:

Verified
Correct Answer:
Verified