Multiple Choice
____ includes determining which risks may adversely affect the project objective and what the impact of each risk might be if it occurs.
A) Risk modification
B) Risk avoidance
C) Risk identification
D) Risk acceptance
Correct Answer:

Verified
Correct Answer:
Verified