Risks ____ should be given higher priority because if the risk occurs, it would have a greater impact on the schedule than if it was associated with activities on a path that has a large positive value of total slack.
A) that occur first in the project
B) that affect the most costly activities
C) on the critical path
D) that affect the activities near the end of the project