Multiple Choice
Fitting a linear trend to 36 monthly data points (January 2000 = 1,February 2000 = 2,March 2000 = 3,etc. ) produced the following tables:
The projected trend value for January 2003 is ___.
A) 544.29
B) 868.61
C) 652.39
D) 760.50
E) 876.90