A line balancing solution has been developed for the assembly line for fertilizer spreaders at Green Grass, Inc.The desired output rate of 30 spreaders per hour will be achieved.The sum of times for all tasks performed on the line is 1200 seconds for each spreader assembled.Which of the following statements must be true?
A) The cycle time is 30 seconds per spreader.
B) The theoretical minimum number of work stations is 10.
C) If the solution calls for 12 stations, the efficiency is 80%.
D) If the solution calls for 11 stations, the efficiency is 80%.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: For a given cycle time in line
Q5: The production of large goods such as
Q6: Services such as legal and medical specialties
Q8: The twelve tasks necessary to assemble a
Q9: A Gallup study showed that workers who
Q10: Which of the following is not a
Q11: The facility layout in a library would
Q25: The predominant layout type used in hospitals
Q37: Cycle time should be smaller than the
Q44: Cellular layouts are designed according to the