An airplane repair facility has a contract to repair cargo aircraft for a regional airline.There are 62 planes in the airline company's fleet of planes.Because of the punishing workload, the planes require a considerable amount of maintenance.The repair facility is trying to determine how to schedule the needed repairs.They want to compare the shortest processing time rule and the first-come first-served rule.Currently, the following planes need repair and are in the repair facility (data given is in order of plane arrival, only one plane is worked on at a time and the shop is open 24 hours a day, 7 days a week).
a.In what order should the planes be repaired using the shortest processing time rule (use first letter of plane)?
b.What is the average time (in hours) in the shop using the shortest processing time rule?
c.What is the average time (in hours) in the shop using the first?come first?served rule?
Correct Answer:

Verified
a.Shortest processing time:
Order of job...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
Order of job...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q14: Johnson's sequencing rule is used to sequence<br>A)several
Q15: Tardiness measures the amount of time by
Q15: Which of the following is not a
Q16: A lateness measure can only be 0
Q17: At the end of each month, a
Q20: High flow times reduce WIP inventory.
Q21: For a single processor, a first-come, first-served
Q22: The time needed to process a given
Q24: Describe Johnson's sequencing rule for the two-resource
Q36: Short-term capacity fluctuations necessitate changes in schedules.