Essay
A print shop has five large commercial printing jobs to finish.They are trying to decide whether to use the shortest processing time (SPT) or the first-come first-served (FCFS) sequencing rule.Data on estimated processing time (in hours) and time to promised completion (in hours) is as follows (jobs shown in order of arrival):
a.What is the average flow time in hours using the FCFS rule?
b.What is the average job lateness in hours using the FCFS rule?
c.What is the average flow time in hours using the SPT rule?
d.What is the average job lateness in hours using the SPT rule?
Correct Answer:

Verified
a.First-come first-served:
Order of jobs...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
Order of jobs...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q5: Flow time is the amount of time
Q21: Explain why any sequence chosen in the
Q35: Rescheduling rarely occurs unless customers change their
Q47: Gantt charts can show what jobs are
Q52: What four (4) decisions are considered in
Q56: The EDD rule minimizes the maximum of
Q57: Which of the following is NOT a
Q58: The numerical difference between the completion time
Q60: The SPT sequencing rule will maximize the
Q76: Explain the three categories of criteria used