Essay
A company wants to develop a project using PERT to modify one of their products which has poor sales.They have determined the following activities, precedence relationships and time estimates in days for the project: a.What is the expected duration for activity a?
b.What is the variance for activity d?
c.How many paths are there in the network?
d.What is the earliest start (ES) time for activity e?
e.What is the slack in days for activity b?
f.What is the critical path?
g.What is the duration of the critical path in days?
h.What is the standard deviation of the critical path?
i.What is the probability that the project will take longer than 28 weeks to complete?
Correct Answer:

Verified
a.te = (to + 4tView Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q2: With the Activity-On-Node (AON) network, the nodes
Q3: Which step in the project management process
Q5: The following network shows all the major
Q6: Which is incorrect regarding the critical path?<br>A)Shortest
Q7: The county government has decided to redo
Q8: Consider the project network and data shown
Q10: We should not crash activities on the
Q13: A Gantt chart is a useful tool
Q38: Describe how a project fits into each
Q96: List at least six principal factors (contributors)