Locksmith Inc.has an order from a bank for 50 specially designed safes, one for each bank branch.It is estimated that the first safe will require 75 hours of shop time and a 90% learning curve is expected.The labor rate is $15.00 per hour and the pricing policy of the company is to triple the labor cost of the order.
a.How many labor hours should the 50th unit require?
b.How many labor hours will the whole order require?
c.What is the customer's price for each safe?
Correct Answer:

Verified
a.Labor hours for 50th safe = (7...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q33: Define work measurement and what it leads
Q43: For a work sampling study, there is
Q45: All of the following are advantages of
Q46: After developing a pre-determined standards, stop-watch or
Q46: Normal time needs to be adjusted for
Q49: Personal fatigue and delay allowances are added
Q50: The _ states that the cost of
Q51: Work standards<br>A)Improve motivation if set by managers<br>B)Increase
Q52: Allowances include time for all of the
Q53: Differentiate between an experience curve and the