The manager at a sewing factory uses a piece rate pay system.She has just received an order for 600 dresses from the discount house downtown.She is trying to figure out what her costs are for the project.She has conducted a time study and found operations take this long:
2 minutes to sew one sleeve
3 minutes to sew body of the dress
3.5 minutes to hem all unfinished edges
1 minute to attach the collar
3 minutes to attach all buttons
The workers must sit idle while they wait for supplies on the conveyor belt for an average of 30 seconds.Their performance rating is equal to one.She pays the workers $6.00 per hour.
a.What is the allowance factor for the operation?
b.What is the labor standard (in minutes) per dress?
c.What is the labor cost per dress?
d.What is the labor cost for the entire order of 600 dresses?
Correct Answer:

Verified
a.Cycle time = 2(2) + 3 + 3.5 + 1 + 3 = ...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q4: Define time study and describe the basic
Q5: Discuss the two different sides of the
Q27: Work samplings<br>A)Are based on normal distribution<br>B)Are used
Q28: Define work sampling.Give both manufacturing and service
Q29: Explain the use of regression analysis in
Q32: For work sampling, p will never be
Q33: Explain the concept of learning curves using
Q34: Determine the sample size for the following
Q35: How do predetermined standards differ from time
Q36: A company manufactures computer parts.They have received