Essay
A cement company has three factories that they identify as Alpha, Beta, and Gamma.They supply cement to three warehouses that they call X, Y, and Z.The company wants to determine how much cement should be shipped from each factory to each warehouse to minimize shipping costs.The cost to ship each 100-pound bag, along with warehouse requirements and factory capacities in bags are shown in the table below:
a.How many decision variables are there in this problem?
b.What is (are) the constraint(s) corresponding to Factory Alpha?
c.How many constraints are required for this problem?
Correct Answer:

Verified
a.9 variables
Xi = each combination of f...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
Xi = each combination of f...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q5: The constraint that requires the beginning inventory
Q6: If R<sub>m</sub> = increase in the total
Q7: <span class="ql-formula" data-value="\sqrt{x}"><span class="katex"><span class="katex-mathml"><math xmlns="http://www.w3.org/1998/Math/MathML"><semantics><mrow><msqrt><mi>x</mi></msqrt></mrow><annotation encoding="application/x-tex">\sqrt{x}</annotation></semantics></math></span><span
Q8: The normal-time project cost does not depend
Q10: If for a given month overtime units
Q11: The Pacific Computer Company makes two models
Q12: (a month's production) + (beginning inventory) -
Q14: A small lumber company in the Southeast
Q27: For linear programming to work for project
Q28: What characterizes a linear function?