Multiple Choice
Exhibit 3.1
The following questions are based on this problem and accompanying Excel windows.
Jones Furniture Company produces beds and desks for college students.The production process requires carpentry and varnishing.Each bed requires 6 hours of carpentry and 4 hour of varnishing.Each desk requires 4 hours of carpentry and 8 hours of varnishing.There are 36 hours of carpentry time and 40 hours of varnishing time available.Beds generate $30 of profit and desks generate $40 of profit.Demand for desks is limited,so at most 8 will be produced.
Let X1 = Number of Beds to produce X2 = Number of Desks to produce
The LP model for the problem is
MAX: 30 X1 + 40 X2
Subject to: 6 X1 + 4 X2 ≤ 36 carpentry)
4 X1 + 8 X2 ≤ 40 varnishing)
X2 ≤ 8 demand for desks)
X1,X2 ≥ 0
-You have been given the following linear programming model.
MAX: 8 X1 + 5 X2
Subject to: 3 X1 + 5 X2 = 54
11 X1 + 10 X2 ≤ 144 X1 ≥12 X2
X1,X2 ≥ 0
This formulation is:
A) not an LP formulation.Pre-processing is required to make it linear.
B) a transportation problem
C) a transshipment problem
D) the assignment problem
Correct Answer:

Verified
Correct Answer:
Verified
Q9: Using Data Envelopment Analysis (DEA) for an
Q12: What does the Excel "=SUMPRODUCT(A1:A5,C6;C10)" function do?<br>A)
Q16: A heuristic solution is<br>A) used by Analytic
Q54: You have been given the following
Q60: Which tab in the Analytic Solver Platform
Q61: Exhibit 3.3<br>The following questions are based on
Q61: A hospital needs to determine how
Q62: State Farm Supply has just received
Q63: The hospital administrators at New Hope,County
Q69: Exhibit 3.1<br>The following questions are based on