Jones Furniture Company produces beds and desks for college students.The production process requires carpentry and varnishing.Each bed requires 6 hours of carpentry and 4 hour of varnishing.Each desk requires 4 hours of carpentry and 8 hours of varnishing.There are 36 hours of carpentry time and 40 hours of varnishing time available.Beds generate $30 of profit and desks generate $40 of profit.Demand for desks is limited so at most 8 will be produced.
How much can the price of Desks drop before it is no longer profitable to produce them? Base your response on the following Analytic Solver Platform sensitivity output.
Let X1 = Number of Beds to produce X2 = Number of Desks to produce
The LP model for the problem is
MAX: 30 X1 + 40 X2
Subject to: 6 X1 + 4 X2 ? 36 carpentry)
4 X1 + 8 X2 ? 40 varnishing)X2 ? 8 demand for X2)
X1,X2 ? 0
Correct Answer:

Verified
The allowa...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q3: The simplex method of linear programming (LP):<br>A)
Q12: What is the value of the slack
Q13: A change in the right hand side
Q24: A formulation has 20 variables and 8
Q29: Benefits of sensitivity analysis include all the
Q30: What is the value of the
Q34: Jones Furniture Company produces beds and
Q34: Analytic Solver Platform provides all of the
Q48: When the allowable increase or allowable decrease
Q71: The coefficients in an LP model (c<sub>j</sub>,