A company wants to select 1 project from a set of 4 possible projects. Which of the following constraints ensures that only 1 will be selected?
A) X1 + X2 + X3 + X4 = 1
B) X1 + X2 + X3 + X4 ≤ 1
C) X1 + X2 + X3 + X4 ≥ 1
D) X1 + X2 + X3 + X4 ≥ 0