If a company selects Project 1 then it must also select either Project 2 or Project 3. Which of the following constraints enforces this condition?
A) X1 − X2 − X3 ≥ 0
B) X1 + (X2 − X3) ≤ 0
C) X1 + X2 + X3 ≤ 2
D) X1 − X2 − X3 ≤ 0