A company wants to build a new factory in either Atlanta or Columbia.It is also considering building a warehouse in whichever city is selected for the new factory.The following table shows the net present value NPV)and cost of each facility.The company wants to maximize the net present value of its facilities,but it only has $15 million to invest.
Variable Decision
NPV
$million)
Cost $million)
X1 Factory in Columbia 3 10
X2 Factory in Atlanta 4 8
X3 Warehouse in Columbia 2 6
X4 Warehouse in Atlanta 1 5
Based on this ILP formulation of the problem and the indicated optimal solution what values should go in cells B6:G14 of the following Excel spreadsheet?
MAX: 3 X1 + 4 X2 + 2 X3 + X4
Subject to: 10 X1 + 8 X2 + 6 X3 + 5 X4 ≤ 15
X1 + X2 = 1 X3 + X4 ≤ 1 X3 − X1 ≤ 0 X4 − X2 ≤ 0
Xi = 0,1
Correct Answer:

Verified
Solution: ...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q16: A company produces three products which
Q20: A cellular phone company wants to
Q24: A city wants to locate 2
Q29: Exhibit 6.2<br>The following questions pertain to the
Q32: The branch & bound algorithm stops when:<br>A)
Q61: Binary variables are:<br>A) a subset of integer
Q68: Variables, which are not required to assume
Q70: Which of the following are potential pitfalls
Q78: Suppose you want to maximize an objective
Q94: The concept of a lower bound in