-There are various similarities between the CPM and PERT methods. Which of the following is not one of those similarities?
A) Any project can be broken down into component activities that require different amounts of time.
B) Any project can be broken down into component activities that must be accomplished in a specific order.
C) Both techniques use the same method to calculate the time element of the activities in the project.
D) Both require a detailed network of the project that clearly indicates each of the main activities and the precedence relationship among the activities.
Correct Answer:

Verified
Correct Answer:
Verified
Q43: Exhibit 14.13<br>The following questions use the information
Q44: Exhibit 14.13<br>The following questions use the information
Q45: Exhibit 15.1<br>The following questions employ the AON
Q46: Exhibit 15.2<br>The following questions employ the AON
Q47: Exhibit 15.1<br>The following questions employ the AON
Q49: Exhibit 15.3<br>The following questions are based on
Q50: Exhibit 15.2<br>The following questions employ the AON
Q51: Exhibit 15.3<br>The following questions are based on
Q52: Exhibit 15.2<br>The following questions employ the AON
Q53: Exhibit 14.13<br>The following questions use the information