Multiple Choice
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.
-The critical path in PERT analysis is the path with the
A) smallest variance.
B) longest expected completion time.
C) smallest number of tasks.
D) smallest variance and longest expected completion time.
Correct Answer:

Verified
Correct Answer:
Verified
Q7: Exhibit 15.1<br>The following questions employ the AON
Q8: Exhibit 15.4<br>The following questions are based on
Q9: Exhibit 15.2<br>The following questions employ the AON
Q10: One of PERT's bold assumptions is that<br>A)
Q11: Exhibit 15.3<br>The following questions are based on
Q13: Exhibit 14.13<br>The following questions use the information
Q14: Exhibit 15.1<br>The following questions employ the AON
Q15: Exhibit 15.2<br>The following questions employ the AON
Q16: Exhibit 15.1<br>The following questions employ the AON
Q17: Exhibit 14.13<br>The following questions use the information