-For an activity with duration t, slack can be calculated as
A) LF-EF
B) LF-t
C) LS+t
D) LS+ES
Correct Answer:

Verified
Correct Answer:
Verified
Q61: Exhibit 15.1<br>The following questions employ the AON
Q62: Exhibit 14.13<br>The following questions use the information
Q63: Exhibit 15.5<br>The following questions use the information
Q64: The critical path is the _ path
Q65: Exhibit 15.6<br>The following questions use the information
Q67: Exhibit 15.3<br>The following questions are based on
Q68: Exhibit 15.2<br>The following questions employ the AON
Q69: Exhibit 15.2<br>The following questions employ the AON
Q70: Exhibit 14.13<br>The following questions use the information
Q71: Exhibit 15.1<br>The following questions employ the AON