Activities with zero slack


A) are dummy activities
B) lie on the critical path
C) must be completed first
D) must be delayed

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q11: Exhibit 15.3<br>The following questions are based on

Q16: Exhibit 15.1<br>The following questions employ the AON

Q26: Exhibit 15.5<br>The following questions use the information

Q29: How many paths are there in the

Q30: Exhibit 15.2<br>The following questions employ the AON

Q33: Exhibit 15.6<br>The following questions use the information

Q34: What are the immediate successors of activity

Q35: Exhibit 15.4<br>The following questions are based on

Q44: Exhibit 14.13<br>The following questions use the information

Q52: Exhibit 15.2<br>The following questions employ the AON

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines