Multiple Choice
Quality risk refers to the chance that:
A) The project relies on developing new or untested technologies.
B) The firm's reputation may suffer when the product becomes available.
C) The well-being of the users or developers may decline dramatically.
D) The firm may face a lawsuit.
Correct Answer:

Verified
Correct Answer:
Verified