Net present value is being used to break the tie among four otherwise equal projects.If the interest rate is 4%,which of these anticipated four-year flows would yield the greatest net present value?
A) $10,000 in year 1;$11,000 in year 2;$12,000 in year 3;and $13,000 in year 4
B) $13,000 in year 1;$12,000 in year 2;$11,000 in year 3;and $10,000 in year 4
C) $10,000 in year 1;$10,000 in year 2;$13,000 in year 3;and $13,000 in year 4
D) $11,000 in year 1;$11,000 in year 2;$12,000 in year 3;and $12,000 in year 4
Correct Answer:

Verified
Correct Answer:
Verified
Q26: A balanced project portfolio may be interpreted
Q27: The Analytical Hierarchy Process is used to
Q28: The simplest method of project screening and
Q29: Evaluating projects in terms of their strategic
Q30: The checklist model of project screening has
Q32: The Analytic Hierarchy Process is being employed
Q33: Inatech is contemplating two different projects
Q34: Which statement about the Analytical Hierarchy Process
Q35: What criteria might be employed to prioritize
Q36: What are the advantages and limitations of