Multiple Choice
The stage of configuration management where the breakdown of the project to the necessary level of definition is identified as:
A) Configuration review.
B) Configuration identification.
C) Status accounting.
D) Configuration control.
Correct Answer:

Verified
Correct Answer:
Verified