Multiple Choice
Cut-Rate Construction Company (CCC) begins building a restaurant for Diners Restaurants, Inc., but after two months demands an extra $100,000. Diners agrees to pay.
-Refer to Fact Pattern 11-3.If CCC offers,as a reason for the extra $100,000,that extraordinary unforeseen difficulties will add considerable cost to the project,the agreement is
A) enforceable as an accord and satisfaction.
B) enforceable because of unforeseen difficulties.
C) unenforceable as an illusory promise.
D) unenforceable due to the preexisting duty rule.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: An obligation is enforceable only if it
Q14: Joel contracts to hire Huong for one
Q16: For consideration to have "legally sufficient value,"
Q18: A promise to pay for an act
Q20: General Credit Corporation promises to pay its
Q26: Milo files a suit against Neighbors Insurance
Q27: Parties are not generally free to make
Q29: Numeric Methods Corporation promises to give stock
Q30: Jean promises to pay Khalil $500 because
Q42: Promissory estoppel requires reliance of a substantial