Multiple Choice
Kip sells an apartment building to Lacy with a promise to repair the roof, which violates the local housing code, within six months. One year later, Kip sends Milo, a carpenter, to fix the roof. Lacy orders Milo to leave and refuses to make further payments to Kip, who files a suit against Lacy.
-Refer to Fact Pattern 15-2.Neil's performance is most likely
A) a material breach.
B) a minor breach.
C) Mutual's breach.
D) no breach.
Correct Answer:

Verified
Correct Answer:
Verified
Q9: Best Construction,Inc.,contracts to build a store for
Q10: Any breach of contract discharges the breaching
Q11: A discharge in bankruptcy will ordinarily bar
Q11: Even-Bilt Construction contracts to build a warehouse
Q30: Anticipatory repudiation discharges a contract.
Q35: Complete performance occurs when conditions in a
Q35: A breach of contract occurs only when
Q36: Most contracts are discharged by rescission.
Q46: A contract is substantially performed when performance
Q62: A promise to perform under a contract