Effective comparative estimates rely most heavily on:
A) An accurate inflation factor.
B) The correct number of years elapsed between the old project and the current one.
C) True comparability between the current project and previous project work.
D) The correct number of employees on the new project compared with the previous one.
Correct Answer:

Verified