Multiple Choice
A contingency rate of 10% on a building project budgeted at $20 million means the project organization is hoping to bring the project in for around:
A) $22 million.
B) $2 million.
C) $18 million.
D) $200 million.
Correct Answer:

Verified
Correct Answer:
Verified