Ray's shipment of materials hit every red light and traffic jam on the way to the site.Upon arrival,half of the material was judged defective,necessitating a trip back to the supplier,and then the same arduous journey back to the site once the new materials were loaded.Traffic was a little better on the second round but the flat tire and subsequent repair caused as much if not more delay than the first trip.In the final analysis:
A) The project activity of Material Delivery was pretty close to the optimistic estimate.
B) The project activity of Material Delivery was pretty close to the most likely estimate.
C) The project activity of Material Delivery had a much higher variance than anticipated.
D) The project activity of Material Delivery was pretty close to the pessimistic estimate.
Correct Answer:

Verified
Correct Answer:
Verified
Q49: An activity has an optimistic time estimate
Q50: A sequence of activities defined by the
Q51: An MBA student laboriously calculated the
Q52: The BEST candidate activities for shortening the
Q53: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -Use the network
Q55: An activity has an optimistic time estimate
Q56: One of the defining points of a
Q57: There's an old saying,"The job is not
Q58: Phoebe B.Beebee is constructing a canal
Q59: A gentleman farmer maniacally works on