-Use the Gantt Chart and Activity List to Determine Which

Question 2

Multiple Choice

   -Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.  \begin{array} { | l | l | l | l | }  \hline \text { Activity } & \text { Resources } & \text { Activity } & \text { Resources } \\ \hline \text { R } & 3,5 & \text { M } & 1,2 \\ \hline \text { H } & 1 & \text { K } & 4 \\ \hline \text { G } & 2,5 & \text { T } & 3 \\ \hline \text { F } & 4,1 & \text { P } & 1 \\ \hline \text { B } & 2 & \text { S } & 3,4 \\ \hline T & 4 & \text { W } & 3 \\ \hline \end{array}  A)  Resource 2 B)  Resource 4 C)  Resource 1 D)  Resource 3
-Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.  Activity  Resources  Activity  Resources  R 3,5 M 1,2 H 1 K 4 G 2,5 T 3 F 4,1 P 1 B 2 S 3,4T4 W 3\begin{array} { | l | l | l | l | } \hline \text { Activity } & \text { Resources } & \text { Activity } & \text { Resources } \\\hline \text { R } & 3,5 & \text { M } & 1,2 \\\hline \text { H } & 1 & \text { K } & 4 \\\hline \text { G } & 2,5 & \text { T } & 3 \\\hline \text { F } & 4,1 & \text { P } & 1 \\\hline \text { B } & 2 & \text { S } & 3,4 \\\hline T & 4 & \text { W } & 3 \\\hline\end{array}


A) Resource 2
B) Resource 4
C) Resource 1
D) Resource 3

Correct Answer:

verifed

Verified

Related Questions