Multiple Choice
If an activity's cost is plotted against its duration on axes with zeros at the origin:
A) The slope of the line is positive because it costs more to finish an activity more quickly.
B) The slope of the line is negative because a shorter activity costs less than a longer one.
C) The slope of the line is negative because it costs more to finish an activity more quickly.
D) The slope of the line is positive because a longer activity costs more than a shorter one.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: The process of accelerating a project is
Q2: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -Use
Q4: The most common type of logical sequencing
Q5: Sketch the network described in the
Q6: The fastest completion time for this project
Q7: Determine early start and early finish times
Q8: The least common type of lag relationship
Q9: The most common method for shortening activity
Q10: The AOA network described by this
Q11: Quite often the marginal gains in employee