Solved

A Project Has the Activity Duration and Cost Information Indicated

Question 19

Multiple Choice

A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $4,000 per week for every week the project exceeds 37 weeks.What is the lowest total cost for completing this project? A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $4,000 per week for every week the project exceeds 37 weeks.What is the lowest total cost for completing this project?   A)  $172,000 B)  $184,000 C)  $187,000 D)  $192,500


A) $172,000
B) $184,000
C) $187,000
D) $192,500

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions