Solved

A Project Has the Activity Duration and Cost Information Indicated

Question 38

Multiple Choice

A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 33 weeks?  Activity  Normal  time  Crash  time  Normal  Cost  Crash  Cost  Predecessor A85$1,0002,000B641,5002,000 A C851,8002,300 AD1291,0001,800 BE14119501,450 BF971,5001,900 C, D G752,3002,800 E, F \begin{array} { | l | l | l | l | l | l | } \hline \text { Activity } & \begin{array} { l } \text { Normal } \\\text { time }\end{array} & \begin{array} { l } \text { Crash } \\\text { time }\end{array} & \begin{array} { l } \text { Normal } \\\text { Cost }\end{array} & \begin{array} { l } \text { Crash } \\\text { Cost }\end{array} & \text { Predecessor } \\\hline \mathrm { A } & 8 & 5 & \$ 1,000 & 2,000 & \\\hline \mathrm { B } & 6 & 4 & 1,500 & 2,000 & \text { A } \\\hline \mathrm { C } & 8 & 5 & 1,800 & 2,300 & \mathrm {~A} \\\hline \mathrm { D } & 12 & 9 & 1,000 & 1,800 & \mathrm {~B} \\\hline \mathrm { E } & 14 & 11 & 950 & 1,450 & \mathrm {~B} \\\hline \mathrm { F } & 9 & 7 & 1,500 & 1,900 & \text { C, D } \\\hline \mathrm { G } & 7 & 5 & 2,300 & 2,800 & \text { E, F } \\\hline\end{array}


A) $11,250
B) $11,500
C) $12,250
D) $12,500

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions