Crashing Costs for a Project Are Governed by the Function

Question 72

Essay

Crashing costs for a project are governed by the function:
50t² + 100t
where t represents the number of days crashed (see graph).The project manager wants to crash the project,and is willing to pay up to $1,000 per day saved.How many days can be saved before the per-day cost is too high? Crashing costs for a project are governed by the function: 50t² + 100t where t represents the number of days crashed (see graph).The project manager wants to crash the project,and is willing to pay up to $1,000 per day saved.How many days can be saved before the per-day cost is too high?

Correct Answer:

verifed

Verified

We can crash the project to the point wh...