menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management
  4. Exam
    Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks
  5. Question
    Dummy Activities Have a Duration Equal to The
Solved

Dummy Activities Have a Duration Equal to The

Question 66

Question 66

Multiple Choice

Dummy activities have a duration equal to the:


A) Slack on the critical path.
B) Length of the predecessor.
C) Length of the successor.
D) Lag needed to preserve network logic.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q12: The BEST approach to network representation of

Q40: For large projects,network diagrams are more useful

Q49: What are four criticisms and caveats to

Q52: What information is NOT included in the

Q55: An activity performed by a subcontractor is

Q62: It costs $75 per day for

Q64: Research has shown that,in general:<br>A)There is a

Q69: What is the minimum completion cost

Q73: A finish to start lag delay is

Q79: In order to accelerate completion of a

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines