    -What Is the Late Finish for Activity D in the Network
Solved

-What Is the Late Finish for Activity D in the Network

Question 15

Question 15

Multiple Choice

  -What is the late finish for activity D in the network shown in the diagram? A) 15 B) 16 C) 17 D) 18
-What is the late finish for activity D in the network shown in the diagram?


A) 15
B) 16
C) 17
D) 18

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q10: The AOA network described by this

Q11: Quite often the marginal gains in employee

Q12: The BEST approach to network representation of

Q13: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -Use

Q14: What is the minimum completion cost

Q16: What is the duration of the project

Q17: A project has the activity duration

Q18: Brook's Law states that the typical crashing

Q19: Gantt charts cannot depict float.

Q20: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -Use

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines