Multiple Choice
Acron Construction charges each customer a price equal to the cost of direct materials and direct labour plus 40%.Job 126 included the following costs:
What price does Acron charge for Job 126?
A) $46,800
B) $65,400
C) $86,000
D) $148,400
Correct Answer:

Verified
Correct Answer:
Verified