Use This Activity Precedence Table to Create a Resource Loading

Question 4

Essay

Use this activity precedence table to create a resource loading profile.Activity lengths are given in days and an 8-hour day is assumed.  Activity  Time  Predecessor  A 2 B 3 A  C 6 B D5 A E3 C  F 2 D G2 E,F \begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 2 & \\\hline \text { B } & 3 & \text { A } \\\hline \text { C } & 6 & \text { B } \\\hline \mathrm { D } & 5 & \text { A } \\\hline E & 3 & \text { C } \\\hline \text { F } & 2 & \text { D } \\\hline G & 2 & \text { E,F } \\\hline\end{array}

Correct Answer:

verifed

Verified

The loading chart is as follow...